How to plan a week when jobs overrun

Jobs run long. A plan that pretends they will not falls over by Tuesday. How to measure your own overrun, add the right slack and tell customers before they ask.

C

Callum Reyes

Customer success, former dispatcher

3 min read

How to plan a week when jobs overrun

Every plan I ever made on a Monday was wrong by Tuesday lunch. A cylinder swap found a corroded valve. A fuse board had no labels. A customer wanted to talk. I used to treat each one as a surprise. After a few years I understood that an overrun is the most predictable thing in the week. Only its address is unknown.

Find out how long your jobs really take

Most price lists carry a time per job type that someone wrote down years ago: boiler service, one hour. Take the last three months of jobs and compare the planned time with the real one, from arrival to leaving. You will find two kinds of job.

  • Steady jobs, such as services and inspections, that finish within ten minutes of the plan nine times in ten

  • Open jobs, such as fault finding, leaks and anything behind a wall, that run over by 30% or more one time in three

Plan them differently. Steady jobs can sit back to back. Open jobs need room after them, and the room has to be in the plan before the day starts.

In numbers

1 in 3

open jobs overran by 30% or more

22 min

median overrun of a fault-finding visit

4 pm

the hour most late arrivals happen when no slack is planned

From 1.1 million jobs completed on Fieldday, Apr to Sep 2026. Open jobs are fault finding, leaks and repairs without a fixed scope.

Put the slack where the risk is

The usual fix is to add 15 minutes to everything. That wastes two hours a day per technician and still fails when a 60-minute job takes 140. A better rule has three parts.

  1. Book open jobs first thing in the morning or straight after lunch, so an overrun eats a break and not a customer.

  2. Follow every open job with a steady one that has a wide arrival window, such as 11:00 to 13:00. The wide window is your slack, and the customer agreed to it.

  3. Never put two open jobs back to back for the same person.

With that rule most days absorb their own trouble. For the days that do not, you need the second half of the plan: what moves, and who is told.

Decide in advance what moves

When a job runs 40 minutes over, the office has three choices: push everything back, hand the next job to someone else, or move one job to tomorrow. Under pressure people push everything back, because it needs no decision. It is also the worst choice, as it makes three customers late and not one.

Agree the order when things are calm. Ours was: first look for a free technician within 15 minutes of the next job. If there is none, move the most flexible job of the afternoon to the next morning and call that customer first. Only then push times back, and never by more than 30 minutes.

“Customers forgive late. They do not forgive silence. A text at 13:10 saying we will be there at 14:30 is worth more than arriving at 14:05 unannounced.”

Sana Idowu, office manager, Tarn Electrical

Tell the customer before they ask

The moment you know a visit will be late, say so, with a new time. Do not wait to see if the technician catches up. In our own records, late visits with a warning got the same review scores as visits that were on time. Late visits without one scored 1.8 stars lower.

Friday is for the leftovers

Keep Friday afternoon lightly booked: 60% at most. Jobs moved during the week land there, along with return visits and the stock check. A week planned at 100% from Monday to Friday is really a plan to work Saturday. Tell the crew on Monday that Friday afternoon is the buffer, and watch how much calmer Wednesday becomes.

Your first job

Put the advice on the board.

Zones, slack, checklists and payment at the door are all built into Fieldday. Try it with your own jobs for 14 days.

Put the advice on the board.

Zones, slack, checklists and payment at the door are all built into Fieldday. Try it with your own jobs for 14 days.

Create a free website with Framer, the website builder loved by startups, designers and agencies.